QUESTION 1

A project manager procures additional resources from a local company. Which of the following-describes this event?

Correct Answer: A

QUESTION 2

A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?

Correct Answer: B
“If you’re working with vendors to perform some or all of the work of the project, it’s critical that they know exactly what you are asking them to do. The statement of work (SOW) details the goods or services you want to procure. In many respects it’s similar to the project scope statement, except that it focuses on the work being procured. It contains the project description, major deliverables, success criteria, assumptions, and constraints”
Excerpt From: Kim Heldman. “CompTIA Project+ Study Guide.” iBooks.

QUESTION 3

A team member was assigned a new task during a meeting. The team member did not complete the task by the end of the phase, and the PM is looking for evidence to escalate the issue. Which of the following documents could help in this situation?

Correct Answer: A

QUESTION 4

The project manager for a TV tower construction project receives notification that a strong storm is expected the following week.
Which of the following should the project manager do NEXT?

Correct Answer: C
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 238

QUESTION 5

Which of the following defines the minimum level of engagement of a stakeholder?

Correct Answer: A