ASF Dumps

ASF Free Practice Test

Exin ASF: EXIN Agile Scrum Foundation

QUESTION 1

How should 'done' be defined when multiple teams are working on a single product?

Correct Answer: A

QUESTION 2

During a Sprint Planning session, the team argues about the work estimates for a particular story.
✑ The Product Owner estimates five days.
✑ The Lead Architect estimates two days.
✑ The Scrum Master estimates eight days.
✑ The team member working on it estimates seven days.
What value (in days) should be used for planning?

Correct Answer: C

QUESTION 3

What is meant by the velocity of the team?

Correct Answer: C

QUESTION 4

A user story was estimated at five ideal hours. On a normal eight hour working day, the team gets about four hours of actual work time.
What would be the elapsed time required to complete the Story?

Correct Answer: A

QUESTION 5

What is an "escaped defect"?

Correct Answer: A